
Mon-Fri 8am-5pm EST
1-800-416-1298
PO Box 647
Exeter, NH 03833
( Physical Address)
16 Kingston Road Unit 4
Exeter, NH 03833
Exterior Framing Continues
With the home’s sub-floor down and the exterior walls framed and up,
the framing crew was on to the roof. Though the roof was rather
simple in structure with just a 12/12 pitch and no valleys it was a
significant framing undertaking due to just the size and height of
it. The house was 32 feet wide by 44 feet in length, and the
exterior side walls stood 11 feet tall in the great room. This
exterior wall height of 11 feet translated into a roof ridge that
was 27 feet off the floor of the great room. Consequently staging
was required to install the ridge pole and roof rafters. In
addition, since the span from the top of the walls to the ridge was
so long, heavy 2x12s were required for the roof rafters. Within a
week, however, the team had completed the installation of the roof
rafters and the house began to take on real shape.
I should comment briefly about the sub-floor and exterior walls
before I move on.
I decided on using ¾” tongue and groove plywood for the sub-flooring
rather than OSB/particle board as I was concerned that the OSB was
too sensitive to moisture. I was concerned about this, both from the
construction phase and from normal home use. I was concerned that
during the construction phase that snow and ice could potentially
lead to damage such as warping. I have seen this before when OSB was
used on sub-flooring. I was also concerned that during the life of
the home, that there could be water incidents, e.g. a leaking
dishwasher or washer machine that also could also lead to water
damage to the floor. I also believe that plywood is stronger and
that it would provide for a more solid and rigid floor.
Regarding the exterior wall framing I used 2x6 construction. This is
typical in New England as the additional wall depth allows for
higher insulation factors; a must in colder climates.
Sheathing the Outside of the Home
In order to get plumbing and electric contractors onto a site
typically they want the home “buttoned up”. This includes the roof
shingled and the doors and windows on. Thus my framing crew moved
onto the exterior sheathing once the walls and roof framing were
complete.
As with the sub-floor, I again chose plywood for the exterior
sheathing for the same reasons mentioned earlier. On the exterior
walls ½” exterior grade plywood was used. On the roof 5/8” exterior
grade plywood was used. I know many builders today use OSB for both
the walls and roof, however, I still believe for stronger
construction plywood is the way to go.
The sheathing effort took about a week to complete. During this time
exterior doors and windows showed up on the site. Staging the
delivery of material reduces theft and insurance risk as well as
keeps a less cluttered construction site. However, as I have
indicated earlier, communication is critical when you are doing
“Just-in-Time” material delivery.
Installing Exterior Doors and Windows
The installation of the doors and windows was a major undertaking
for this project as the lake side view of the home was literally a
wall of windows; 32 feet in width and 27 feet in height. A great
deal of engineering had gone into the window design so that the 10
large custom windows would fit together like a jig saw puzzle. This
said, when the windows arrived on site and were inspected, it was
determined that some of them were not built correctly to the
dimensions specified. After much debate with the framing crew, the
window vendor and me we reached a compromise on sharing the cost of
fixing the windows. The window vendor took back the improperly sized
windows and the framing crew began the installation of the doors and
what windows they could install. Fortunately the window vendor was
able to return to the site with the properly sized windows within a
few days and the construction phase did not miss a beat.
Completing the Interior Framing
With the doors and windows installed, the framing crew proceeded to
complete the Interior Framing. This was an exciting time, as the
rooms began to take real shape. You could now walk down hallways and
into bedrooms and closet areas. Within just a few days the interior
walls were complete and the framing crew proceeded onto the roof for
the shingling.
I should note that 2x4 construction was used on the interior walls
as insulation was not required on the interior walls.
Shingling the Roof
The last task to complete before the house could be classified as
“Buttoned Up” was to install the shingles on the roof. Fortunately
my framing crew was also able to do this task, thus eliminating the
need for yet another subcontractor.
I chose a 30 year architectural shingle due to the quality and look
I was trying to achieve on the home.
Though relatively a simple roof, it was quite large and the weather
was less than hospitable. Consequently it took nearly 2 weeks to
complete this task. However, with the roof complete, my electric and
plumbing contractors were now able to begin their work.
Also, with the main house now structurally complete, the framing
crew moved onto the garage framing and construction phase. As a
result of staging the garage behind the main home construction
phase, I was able to have subcontractors work in parallel without
getting in each others way.
Rough Electric and Plumbing
With the house “Buttoned-Up”, my Electric and Plumber subcontractors
showed up to begin the roughing in phase of their respective tasks.
Rough Electric
I had met a few days before on site with the Electric subcontractor
to discuss the placement of all the wall outlets and switches, as
well as where the light fixtures would be situated. During our
discussion he marked the wall studs for the placements of the
electric wiring boxes so that we could visualize the entire electric
wiring scheme. We also marked where the telephone and cable boxes
would reside.
During the electrical rough in wiring phase, the electrician
installed all the wiring boxes and ran wire from the boxes to where
the main circuit panel box would reside.
Rough Plumbing
As with the Electrical Subcontractor, I had met several weeks
earlier with the Plumbing Contractor. During this meeting we
discussed the form of heat for the home, as well as where the
bathrooms and kitchen were to reside in the home. We also discussed
types of bathroom fixtures including tubs, sinks and toilets.
Consequently, when he showed up on site he new exactly where to run
main drain and supply pipes and vent stacks. He also roughed in all
of the plumbing for each bathroom and kitchen plumbing fixture.
Within a week both the Electrical and Rough Plumbing contractors had
completed their tasks and had successfully passed their respective
inspections.
To Be Continued ….
In Part 4 of “Building Your Dream House”, Electric and Plumbing
continue and the Kitchen Design is explained. Stay tuned...
About the Author:
D. Benjamin Castonguay is the owner of iapsales.com
LLC - a family business specializing in
HVAC products. We are distributors of
Qmark Heaters,
electric
tankless water heaters, bathroom
heaters, patio heaters,
electric heaters,
portable air
conditioners &
electric towel warmers. Shop on line at
www.heateroutlet.com for these great home improvement products.
Iapsales.com LLC was established in 2003 and is the sister company to Innovative Air Products located in historical Exeter, NH. We are a 2nd generation manufacturers’ rep firm dedicated to providing residential & commercial heating, ventilation and air-conditioning equipment. We offer a great selection online at the lowest prices anywhere. We can also be found on Facebook, Twitter and YouTube.